Wigan borough restoration site now operating entirely on renewable energy

The old gas engines were oversized for the amount of gas now generated from the landfill site and the electricity generated was simply being exporting to the national grid rather than being used on site. The new solution uses a more efficient engine and the electricity produced will now be used onsite.
Watch more of our videos on Shots! 
and live on Freeview channel 276
Visit Shots! now

Green Earth Developments Group has worked with Sterling Capital Asset Finance Ltd., Environ Consultants Ltd. and Landfill Projects Ltd. to upgrade the landfill gas engines and electrical circuits at the Whitehead Restoration Site.

The old gas engines were oversized for the amount of gas now generated from the landfill site and were running at <25% efficiency, causing significant energy losses. In addition, the electricity generated was being exporting to the national grid rather than being used on site.

Hide Ad
Hide Ad

The new solution uses a smaller more efficient containerised Scania 250kW engine that will now operate at >90% efficiency. Importantly, the electricity produced will now be used onsite for the leachate plant and other site services.

New Engine At Whitehead RestorationNew Engine At Whitehead Restoration
New Engine At Whitehead Restoration

Previously the engines generated 2000 MWh of electricity per year. The site currently uses ca. 750MWh a year so we expect the site will therefore now run 100% off the electricity generated from the waste landfill gas. The capture, cleaning and utilisation of landfill gas for power generation is classed as renewable energy.

Mike Walsh, Managing Director at Green Earth Developments Group said: "As a purpose driven company with sustainable solutions at the heart of our proposition we recognised how important it is that we transition to renewable energy across our organisational activities and minimize our carbon footprint. This project is one of a number in our journey to maintaining sustainable and efficient operations at the company's flagship site in Astley, Wigan. It is also a critical part of our journey to becoming a B-Corp certificated company."